Vifon Hai Duong ensures the progress and professional construction...
In March 2017, Unicons, as the General Contractor, officially commenced the construction of Vifon Factory Hai Duong. Only after over 01 month of implementation, until now, the manufactured steel structure quantity has reached 30%, Unicons Steering Board was promptly preparing for assembly and erection of steel structures for 6m high floor, its area is about 7.500 m2 on April 20, 2017